Somalia: ‘I sold the last three goats, they were likely to die’Read more Merck Foundation and African First Ladies marking World Cancer Day 2023 through 110 scholarships of Oncology Fellowships in 25 countriesRead more Supporting women leaders and aspirants to unleash their potentialRead more Fake medicines kill almost 500,000 sub-Saharan Africans a year: United Nations Office on Drugs and Crime (UNODC) reportRead more Climate crisis and migration: Greta Thunberg supports International Organization for Migration (IOM) over ‘life and death’ issueRead more United Nations (UN) Convenes Lake Chad Countries, Amid Growing Regional CrisisRead more 11 Disruptive Startups Selected for Cohort 3 of the Africa Startup Initiative Program (ASIP) Accelerator Program powered by Startupbootcamp AfricaRead more Africa Data Centres breaks ground on new Sameer facility in NairobiRead more Coffee with a human face: A union that improves livelihoods for Ugandan farmersRead more Trends Predicted to drive the retail industry in 2023Read more

NASA eyes two more dates in September for possible Moon launch

show caption
The Artemis 1 space mission hopes to test the SLS as well as the unmanned Orion capsule that sits atop, in preparation for future Moon-bound journeys with humans aboard./AFP
Print Friendly and PDF

Sep 09, 2022 - 09:13 AM

WASHINGTON — NASA is looking at September 23 and September 27 as possible dates for its next attempt at launching its Artemis 1 mission to the Moon, senior official Jim Free told reporters Thursday.

Two previous attempts were scrapped after the giant Space Launch System rocket experienced technical glitches including a fuel leak.

The launch window for the 23rd would open at 6:47am (1047 GMT), while the 27th would open at 11:37am (1537 GMT), added Free, associate administrator for the agency’s exploration systems development directorate.

The dates were chosen to avoid a conflict with the DART mission, in which a probe will strike an asteroid on September 26 to test its ability to divert the object.

Both missions require use of an international array of antennas called the Deep Space Network.

The launch dates still depend, however, on NASA receiving a special waiver to avoid retesting batteries on an emergency flight system that is used to destroy the rocket if it strays from its designated range to a populated area.

If it does not receive the waiver, the rocket will have to be wheeled back to its assembly building, pushing the timeline back several weeks.

Mike Bolger, exploration ground systems manager, added that teams were working to replace seals to fix the hydrogen leak issue — work that could be completed by the end of Thursday, which would pave the way for a tanking test on September 17.

The Artemis 1 space mission hopes to test the SLS as well as the unmanned Orion capsule that sits atop, in preparation for future Moon-bound journeys with humans aboard.

Once launched, it will take several days for the spacecraft to reach the Moon, flying around 60 miles (100 kilometers) at its closest approach.

The capsule will fire its engines to get to a distant retrograde orbit (DRO) of 40,000 miles beyond the Moon, a record for a spacecraft rated to carry humans.

The trip is expected to last several weeks, and one of its main objectives is to test the capsule’s heat shield, which at 16 feet (5 meters) in diameter is the largest ever built.

Artemis is named after the twin sister of the Greek god Apollo, after whom the first Moon missions were named.

The next mission, Artemis 2, will take astronauts to the Moon without landing on its surface, while the third — set for the mid-2020s — would see the first woman and person of color on lunar soil.

NASA wants to build a lunar space station called Gateway and keep a sustained presence on the Moon to gain insight into how to survive very long space missions, ahead of a mission to Mars in the 2030s.

MAORANDCITIES.COM uses both Facebook and Disqus comment systems to make it easier for you to contribute. We encourage all readers to share their views on our articles and blog posts. All comments should be relevant to the topic. By posting, you agree to our Privacy Policy. We are committed to maintaining a lively but civil forum for discussion, so we ask you to avoid personal attacks, name-calling, foul language or other inappropriate behavior. Please keep your comments relevant and respectful. By leaving the ‘Post to Facebook’ box selected – when using Facebook comment system – your comment will be published to your Facebook profile in addition to the space below. If you encounter a comment that is abusive, click the “X” in the upper right corner of the Facebook comment box to report spam or abuse. You can also email us.